The project is planned to be started
from Jan 2011. The total timeline for the project is
18 Months for phase II.
After starting in Jan 2011 about 3 months will be required
to reach upto plinth level. Followed by which three
months each for each floor (including RCC, brickwork,
plastering, flooring, finishing etc.) Hence for 4 floors
total of 12 months will be required. Additional 3 months
for site development, installation of services like
fire fighting, water supply, lifts electric connection
etc. Marketing and sale of project will be done from
April 2011onwards when the project will reach unto plinth
level.
It is expected that entire construction on 4 floors
for about 17800sqft along with site development shall
be completed within 18 months approximately.
|